REPowerEU directive slashes solar permitting times, establishes renewables ‘go-to areas’

Facebook
Twitter
LinkedIn
Reddit
Email
The EU’s response to the war in Ukraine, REPowerEU, aims to relieve dependence on Russian gas and streamline renewables deployment. Image: Glyn Lowe via Flickr.

The EU will introduce shorter permitting times for solar and renewable energy assets in the most recent addition to its REPowerEU scheme, agreed on by the European Council this week.

Solar projects in particular have been singled out to have a permit-granting period of no more than three months, a move that builds on the EU’s recently announced emergency regulation to reduce permitting for solar mounted on artificial structures, as well as associated storage systems and grid connections, to a maximum of one month.

This article requires Premium SubscriptionBasic (FREE) Subscription

Unlock unlimited access for 12 whole months of distinctive global analysis

Photovoltaics International is now included.

  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Unlimited digital access to the PV Tech Power journal catalogue
  • Unlimited digital access to the Photovoltaics International journal catalogue
  • Access to more than 1,000 technical papers
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

The new announcement introduces renewable “go-to areas”, which the European Council describes as “land, sea or inland waters… chosen because they are particularly suitable areas for specific renewable energy technologies and present lower risks for the environment”.

EU member states will be required to map out and designate the “go-to areas” within 30 months of the new directive coming into force, and will adopt measures to mitigate any adverse environmental effects brought about by introducing renewable energy assets to the designated zones.

A major time-saving measure in the new directive sees the whole of a nation’s plans submitted for environmental approval as one body, rather than assessments of each individual project that are currently required.

The EU would also invoke “overriding public interest” in the case of projects in renewables “go-to areas”, assuming they are of significant public interest to minimise grounds for legal objections. The same principle was applied in November’s emergency solar regulation.

“Faster permitting in areas that can yield the best results without harming the environment will allow us to deploy renewable energy in our grids faster. This is the best way of becoming independent of Russian energy and it will also contribute considerably to our climate goals,” said Jozef Síkela, Czech minister of industry and trade.

Non-solar renewables projects within “go-to areas” must undergo permitting within a year, and offshore projects within two. Repowering existing plants and new projects with less than 150kW capacity and any associated energy storage systems or grid connections must undergo the process within six months, or one year if they are offshore projects. The permitting time caps are doubled for projects outside of “go-to areas”.

Whilst explicit permitting decisions will be required, the European Council said that member states could regard a lack of reply regarding a permit as a tacit agreement to intermediary steps.

The time taken to build assets, establish grid connections or related grid infrastructure will not be included in the permit-granting periods.

The European Council confirmed its target of 40% renewables generation by 2030, with solar poised to be a significant part of that.

This week, a report from SolarPower Europe revealed that the EU’s solar deployment had risen 47% in 2022, largely due to the effects of the REPowerEU scheme and other responses to the war in Ukraine.

The European Solar PV Industry Alliance was also recently launched, aiming to establish 30GW of domestic PV manufacturing in Europe by 2025.

21 May 2025
London, UK
The Renewables Procurement & Revenues Summit serves as the European platform for connecting renewable energy suppliers to the future of energy demand. This includes bringing together a community of European off-takers, renewable generators, utilities, asset owners, and financiers. The challenges ahead are complex, but through collaboration, innovation, and a shared vision, we can navigate uncertainties and forge a sustainable energy future. Let us harness our collective knowledge to advance the renewable energy agenda.
3 June 2025
Messe Stuttgart Stuttgart, Germany
Meet battery manufacturers, suppliers, engineers, thought leaders and decision-makers for a conference and battery tech expo focused on the latest developments in the advanced battery and automotive industries. Stay plugged in for all the latest information on The Battery Show Europe 2024 including: Keynote Speakers & Conference Overview Show Features Floor Plan & Exhibitor News Travel & Transport information
17 June 2025
Napa, USA
PV Tech has been running PV ModuleTech Conferences since 2017. PV ModuleTech USA, on 17-18 June 2025, will be our fourth PV ModulelTech conference dedicated to the U.S. utility scale solar sector. The event will gather the key stakeholders from solar developers, solar asset owners and investors, PV manufacturing, policy-making and and all interested downstream channels and third-party entities. The goal is simple: to map out the PV module supply channels to the U.S. out to 2026 and beyond.
2 December 2025
Málaga, Spain
Understanding PV module supply to the European market in 2026. PV ModuleTech Europe 2025 is a two-day conference that tackles these challenges directly, with an agenda that addresses all aspects of module supplier selection; product availability, technology offerings, traceability of supply-chain, factory auditing, module testing and reliability, and company bankability.
10 March 2026
Frankfurt, Germany
The conference will gather the key stakeholders from PV manufacturing, equipment/materials, policy-making and strategy, capital equipment investment and all interested downstream channels and third-party entities. The goal is simple: to map out PV manufacturing out to 2030 and beyond.

Read Next

Premium
April 17, 2025
As Europe readjusts to a new geopolitical uncertainty, PV Tech asks what impact the continent's solar industry might feel.
April 16, 2025
US residential solar company Complete Solaria will change its name to SunPower, resurrecting the name of one of the US' longest-running solar companies which folded last year.
April 16, 2025
Ofgem will remove 'zombie projects' from the country's grid connection queue and streamline the connection process for new projects.
April 16, 2025
Australian mining giant Fortescue Metals Group announced today (16 April) that construction has started on a 190MW solar PV plant at its Cloudbreak site in Western Australia.
April 16, 2025
Europe completed power purchase agreements (PPAs) for 1.6GW of renewable energy capacity in March, according to Pexapark.
Premium
April 16, 2025
In this blog, PV Tech explores how the upcoming Australian federal election could impact the rollout of renewables and solar PV.

Subscribe to Newsletter

Upcoming Events

Media Partners, Solar Media Events
April 23, 2025
Fortaleza, Brazil
Solar Media Events
April 29, 2025
Dallas, Texas
Media Partners, Solar Media Events
May 7, 2025
Munich, Germany
Solar Media Events
May 21, 2025
London, UK
Solar Media Events
June 17, 2025
Napa, USA